500kV Substation Project in Central Alberta

500kV SUBSTATION PROJECT in CENTRAL ALBERTA

PROJECT DETAILS

OWNER:

LOCATION:

AWARD:

START DATE:

GENERAL:

ATCO

Red Water, Alberta

N/A

N/A

Siemens Canada Ltd.

ABOUT THE PROJECT

In delivering this major Substation foundation project, Valard Foundations installed 2,268 piles. Our crew of 11 personnel and 3 Junttan Piling Units, were utilized in completing this project. Additional services rendered include but are not limited to:

  • Material hauling & logistics;
  • Engineering + Survey services & As-builts;
  • Pile installations;
  • Cap cutting, setting & welding;
  • QA/QC; and
  • Site safety.