500kV Transmission Line Project NE Manitoba

500kV TRANSMISSION LINE PROJECT in NE MANITOBA

PROJECT DETAILS

OWNER:

LOCATION:

AWARD:

START DATE:

GENERAL:

Manitoba Hydro

Thompson to Gillam, Manitoba

N/A

January 2016

Valard Construction

ABOUT THE PROJECT

Valard Foundations completed installation of helical foundations to support this 500 kV HVDC transmission line. Scope of work included 2,800 helical anchor / piles.  We also conducted a joint venture with Crux Subsurface to install 30 micropile tower foundations.

Over 20 personnel, 6 helical pile units, and 2 micropile units were utilized in the delivery of this project. Micropiling was utilized in areas of rock and bony tills.