AltaLink

Calgary, Alberta

December 2012

February 2013

Allteck Line Contractors

ABOUT THE PROJECT

15 caissons for new transmission line diameters ranging from 2440mm-3050mm and depths from 12m to 19m large diameter casings were installed and extracted with the use of a vibratory hammer on the 3050mm shafts due to poor soil conditions.