Leduc Transmission Project

LEDUC TRANSMISSION PROJECT

PROJECT DETAILS

OWNER:

LOCATION:

AWARD:

START DATE:

GENERAL:

AltaLink

Leduc to Calmar, Alberta

June 2012

August 2012

Allteck Line Contractors

ABOUT THE PROJECT

28 caissons for monopole foundations with diameters ranging from 1934-2440mm in diameter up to depth of 19m. 40 steel casings were installed with the use of a vibratory hammer then cleaned out with conventional rotary drill rig the steel casings were used for direct embedment poles due to poor soils conditions.